Construction starts on geotechnically challenging N17 freeway link for 2010 World Cup

Pequenino,F.P. April 2008. In SAICE Civil Engineering

This article discusses some of the numerous geotechnical challenges presented along a relatively short freeway link constructed to provide much needed access from the N1 to Soweto and the Soccer City and Orlando Stadiums for the 2010 World Cup. Besides several large bridges over challenging geological terrain, there are deep cuts through existing tailings deposits, shallow undermining and a significant portion of the route constructed over and utilising existing tailings.

N17 NASWETO

FREEWAY

April 2008

Construction has recently started on the new N17 freeway link in Soweto, with site establishment and enabling works underway. The 5,8km freeway link will provide a much needed access from the N1 to Soweto and the Soccer City and Orlando Stadiums.  The approximately R400million design and build contract is a contractor-consultant joint venture between Group 5 and Vela VKE with funding provided by SANRAL and is programmed to be completed before the FIFA 2010 World Cup.

The project presents numerous geotechnical challenges along the relatively short link road; besides several large bridges over challenging geological terrain, there is a deep cutting through an existing tailings dam, a large fill constructed with tailings, some shallow undermining and a significant portion of the route constructed on an existing tailings dam and in close proximity to two other large tailings dams.

All of this is not forgetting the challenges in constructing a road pavement structure on tailings, the aggressive nature of the soils and water in the area towards concrete and cement, together with the regular challenges of delivering such a project to a tight design  and construction programme.

Route and Project Description

 

The figure above shows the  N17 Link road alignment.  The two lane dual carriageway (four lanes in total) tees onto the Soweto Highway at Klipspruit Valley Road (near Orlando Stadium) and for the first 1,5km is aligned in the floodplain of the Klipspruit  whilst dipping below the existing New Canada Railway and later New Canada Road. Here four bridges are provided, one of which will be a large twin portal bridge with spans of 11m which is to be jacked below the railway line.

The remainder of the route is aligned west-east towards Nasrec Road, through a derelict mining area; crossing shallow undermined land and cutting through an existing tailings dam in which two substantial cuts are located. It is here, between the two cuttings, that the N17 crosses over the existing N1( Western Bypass) and a partial interchange is provided with north-facing access to the N1 only.  It is also here that the route approaches the currently operational Mooifontein and Diepkloof tailings dams.  Finally, the road tees in the east with Nasrec Road with a large at grade roundabout provided and with some upgrading and widening of Nasrec Road to improve access to the nearby Soccer City.

Historical background to project

The proposed N17 link is part of a future through route linking the current end of the existing N17 Toll Freeway at Wemmer Pan through the Witwatersrand  mining belt in Johannesburg to Mogale City (Krugersdorp) in the west.  Extensive planning and design of the N17 was undertaken in the 1980s and early 90s by various consultants for the then South African Roads Board, with most of the current link road section corresponding to the section designed by BKS and a small section by Vela VKE.

Although there are benefits to implementing the full N17, in particular that it would provide an important east-west link south of the M2 Motorway, the route’s location through a built up area makes this expensive.  

 

Geotechnical Challenges

The current project presents several geotechnical challenges over the relatively short section of road being constructed. This in itself also highlights the limitations which could be extended to the full route.  Some of these challenges include;

  1. Shallow undermining over part of the route.  Fortunately for the Link road this only occurs over a small section of the route, less than 50m. The stopes have been dewatered and are currently being backfilled using sand/ cement slurry.

  2.  Materials balances. The shortage of adequate quantities of suitable road building materials has required several iterative adjustments to the vertical alignment and to the cut and fill side slopes implemented, in order to optimise the materials usage. One such example is where the N17 cuts under New Canada Road; hard rock quartzite is encountered at shallow depth and the cut is designed deeper, wider and with shallower side slopes in order to generate additional good quality materials.  The shortage of suitable road building materials has also necessitated the use of tailings for the construction of some of the fills.

  3. Shallow rock and outcrop. It is seldom that shallow rock and in this instance hard rock quartzite presents a problem for foundations and indeed two of the six bridges on the route are founded on conventional spread footings at shallow depth. However, when the shallow rock is dipping steeply and a large bridge is to be constructed and then jacked across the dip on strike it results in significant excavations being required and also affects the height of the bridge. Normal bridge clearance heights are in the order 5,2m but the dipping rock has added an extra 3m to the bridge height, at the southern abutment where rock levels are much deeper. This makes the bridge to be jacked under the railway a significantly larger structure and one of the largest bridge jackings yet to be undertaken in the country.  Shallow rock is also encountered at the site of the fourth bridge at New Canada Road and spread foundations will mostly be used. However because of the presence of a 10m wide, near vertical diabase dyke, which presents as a weak compressible soil an innovative arched spread foundation (arching over the weak dyke and transferring most load to the quartzite) is proposed.

  4. Bridges on weak compressible soils; A much more significant diabase dyke is also encountered at the site of the N1/N17 bridge and interchange. Here weak compressible soils are encountered to depths of up to 30m where rock is encountered. The design has also needed to account for the negative skin friction forces resulting from the approach fills placed on the highly compressible soils. A driven precast pile solution is proposed at this bridge and at the sixth bridge, where compressible soils are also encountered, but to shallower depths.

  5. High fills on compressible soils; The compressible soils also result in challenges where high fills (of up to 14m) are constructed thereon. In one instance settlements of up to 250mm are predicted with most of the settlements taking in excess of a year to occur.  The construction of these particular fills will be prioritised so that the settlements occur during construction and prior to the construction of the road pavement.

  6. Existing tailings dams; For much of the route the N17 is in close proximity to the operational Mooifontein and Diepkloof Tailings Dams. The dams’ current heights are in the order of 30-40m and their proposed final heights will be up to 60m. The link road comes as close as 150m to the toes of these dams and falls within the “zone of influence” of the dams.  Detailed analysis has been undertaken and the design of the dams gives no cause for concern, provided of course that the dams continue to be managed and operated to accepted norms and standards.

  7. Contaminated soils and water; Testing on tailings, ground water and surface water show that all of these will be highly aggressive towards steel, concrete and cement (e.g. when used in stabilised layers) and several mitigating measures will be implemented.  These include the use of high durability concrete for “very severe” environmental exposure conditions as well as increased cover and smaller design crack widths.  In addition, bituminous coatings will be applied to concrete exposed directly to tailings and a buffer layer will be provided between any tailings and stabilised pavement layers.

The N17 Link Road project has been selected as the part of the N17 which will best serve the demands of the 2010 World Cup while improving access to Soweto. It presents numerous geotechnical and materials challenges which are rarely encountered on a single project over such a short length. The variability of geotechnical conditions and materials used has required a relatively flexible design which can be reviewed and adjusted as conditions present themselves during ongoing investigations and construction.

OVERCOMING GEOTECHNICAL

CHALLENGES

The project presented several geotechnical challenges over the relatively short section of road constructed. Some of these challenges included;

  1. Shallow undermining over part of the route,

  2. Shortage of good quality fill materials,

  3. Shallow rock and outcrop,

  4. Bridges on weak compressible soils,

  5. High fills on compressible soils,

  6. Existing tailings dams,

  7. Contaminated soils and water.

Next

Previous

  • Facebook - Black Circle
  • LinkedIn - Black Circle
  • Instagram - Black Circle